L7B&BB preparations
31 de outubro de 2023, North Sea ⋅ ☁️ 11 °C
On the last day of October we completed a 3 week preparation campaign on L7B/BB.
This iconic platform is our most challenging; home to a large seagull colony we had to wait for the breeding season toLeia mais
First cargo barge arrived
13 de setembro de 2023, Noruega ⋅ ☀️ 12 °C
Our 3 satellite topsides arrived at AF environmental Base in Norway. A calm and safe trip of about 420 nautical miles (750 km) in about 70 hours.
L7N Topside Lift
21 de agosto de 2023, North Sea ⋅ ☀️ 18 °C
Today, Matador 3 lifted the L7N topside and brought it back to Den Helder. It is the first heavy lift of the project after the removal campaign. Crew and vessel have been ready since the replacementLeia mais
First Prep campaign completed
21 de junho de 2023, North Sea ⋅ ☀️ 15 °C
After 12 week of preparation works, the Seajacks Hydra completed its works with removal of the L7Q-L7C bridge.
Now, 5 complete topsides and 5 topside modules are 100% ready for removal.
Matador 3 willLeia mais
Preparation works at L7CC
22 de maio de 2023, North Sea ⋅ ⛅ 13 °C
After more than 3 weeks warming-up with preparation works at the three satellites, now it's time to get started at the L7CC location!
Considered as the most complicated and lengthy part of the L7Leia mais
Conductor removal scope at L7H
24 de abril de 2023, North Sea ⋅ 🌬 7 °C
Currently jacked-up at L7H, the Hydra now faces an extended scope, now including the removal of the three (3) conductors.
Cut during the P&A campaign at -6 meters below seabed, these conductorsLeia mais
2nd Satellite, L7N in preparation!
19 de abril de 2023, North Sea ⋅ 🌬 9 °C
After a successful preparation campaign at L7A, Hydra is now jacked-up at L7N for similar preparation works.
On the agenda for a week: lifting points inspection, topside legs pinning, topside/jacketLeia mais
L7A Completed, off to L7N
16 de abril de 2023, North Sea ⋅ ☁️ 8 °C
After a week and a half, the prep works on L7A were completed. These first steps were a bit wobbly and early April threw in a good breeze, but we are ready for the next one!
Arrival at L7A
5 de abril de 2023, North Sea
Early morning arrival at L7A with perfect weather conditions. It took some time to move in and Jack-up the vessel and we got to do our initial safety round by late afternoon. Preparations for theLeia mais
Mobilizing Hydra
2 de abril de 2023, Inglaterra ⋅ ☀️ 6 °C
After only 6 months of engineering and work preparation, the L7 project is mobilizing in Tees for the start of the 2023 campaign. Crew, materials and vessel getting ready to sail to the L7 field.
Subsea works - First pipes for disposal!
23 de fevereiro de 2023, Países Baixos ⋅ ☁️ 8 °C
On February 23, the first pipe sections removed from the L7-A and L7-N platforms have been offloaded at Den Helder!
Although pre-measured onboard to verify the NORM free status of the pipes, aLeia mais
Subsea works - L7-A first lifts!
16 de fevereiro de 2023, North Sea ⋅ 🌬 8 °C
Starting at L7-A, the first offshore lifts have been performed within 2 days of arriving at site.
Completely diver-less, these operations have been successfully executed by an ROV (Remote OperatedLeia mais
Subsea operations mobilization date!
11 de fevereiro de 2023, Noruega ⋅ 🌬 7 °C
On the 11th of February, the 1st offshore removal campaign started after more than a year of tendering, engineering and preparation!
Plan is to disconnect all the jackets of the L7 field from anyLeia mais
EBS eDNA sampling, or innovation!
13 de novembro de 2022, North Sea ⋅ 🌬 14 °C
Not yet highly developed in the North Sea, the eDNA sampling and analysis techniques have been established during the L7 EBS project.
The advantages? An ultra accurate representation of theLeia mais
EBS Offshore operations at L7
28 de outubro de 2022, North Sea ⋅ 🌬 16 °C
With more than 70 specific environmental stations to fully cover the L7 field, the EBS is focused on the platform's close surroundings, and up to 50 meters away, and also the OBM wells and infieldLeia mais
EBS Mobilization Day!
25 de outubro de 2022, Inglaterra ⋅ ☁️ 14 °C
As part of the full L7 Site Restitution project, a dedicated Environmental Baseline Study (EBS) will be carried out.
The aim: assessing the current environmental status of the L7 field after moreLeia mais
L7 EPRD Contract signature !
11 de outubro de 2022, Noruega ⋅ ☁️ 9 °C
On the 11th of October 2022, the TEPNL project team together with Aurélie Abiad, Managing Director of the affiliate, joined AF Offshore Decom at their Dismantling yard in Vats to officialize the EPRDLeia mais