Foreword.
7 aprile 1985, Australia
Easter 1985. We first discussed the possibility of moving to Molyullah.
Janette has known Molyullah all her life because of her Uncle Lex living here.
I first came when I met Janette in 1976.
FromLeggi altro
Lex Devitt.
8 aprile 1985, Australia
Lex was a Melbourne boy, born and bred. He lived in North Caulfield with his parents and two older sisters. He attended Caulfield Grammar School.
He was an apprentice at Kelly and Lewis Engineering inLeggi altro
The site.
25 ottobre 1989, Australia
The first site we considered was near the stone hut. We even fenced off a block and planted fruit trees. Access in wet weather might have proved difficult though.
It was then decided that our currentLeggi altro
The shed and the power.
1 novembre 1990, Australia
Lex got the power on in 1987. It came from Irene and Robert Erskine's line which comes in from Tatong.
It required seven poles, two on the Erskine’s' and five on Lex's.
That meant we would need onlyLeggi altro
September 1996 - a start at last.
1 settembre 1996, Australia ⋅ 15 °C
I 'retired' and moved up in August 1996. We had sold our house in Nth Dandenong. Janette continued to work at PFD while living with her Mum, Paula Lee during the week. PFD didn't want to lose JanetteLeggi altro
The slab.
1 dicembre 1996, Australia
Once the site was levelled and the house footprint could be properly accommodated, it was time to think about the slab.
Ross McMahon was to pour the slab and he brought out formwork and set itLeggi altro
The frame arrives.
14 dicembre 1996, Australia
We had a call that the steel frame would be leaving Melbourne on Friday. Because it was oversize, it couldn't leave until after the peak hours had finished.
Doug, the PFD rep from Mansfield, came onLeggi altro
Erection.
20 dicembre 1996, Australia
Stuart, the manager at Dahlsens who organised our steel frame, and Boris, one of their builders, came up for a weekend to help erect the frame. They volunteered, saying a weekend in the country wouldLeggi altro
Meanwhile, back at the shed.
15 gennaio 1997, Australia
The frame is well advanced, and so is organising the next stages:-
*brickies sand, lime, cement, bricks for the chimney, blue foil insulation and brick ties - we have to supply everything. TheLeggi altro
We have a frame!
7 febbraio 1997, Australia
Frame inspection - passed!
8/2/97 took delivery of:-
Jotul wood heater
Stanley kitchen stove
Jetmaster open fire.
The stonies are booked in.
9 febbraio 1997, Australia ⋅ ⛅ 22 °C
Once the frame was finished, we called David Broadhurst, our stoney, to let him know we were ready.
Everything now depended on what he had on. We were now totally dependant on when he would beLeggi altro
Woo hoo - we have a loo!
1 marzo 1997, Australia
The only loo at the shed was a 'porta-potty'. With three stonies likely to be living here for a while, I would be emptying it every couple of days.
I bought a pan and installed it in the toilet at theLeggi altro
March 11th 1997 - first stones are laid.
11 marzo 1997, Australia
David (the boss), Andrew and Sandy laid the first stones today.
David worked inside on the wall, fireplace and chimney. Andrew started on the SW corner of the living room. Sandy started on the cornerLeggi altro
The cost of being a snorer.
21 marzo 1997, Australia
Snorers always seem to be the first to go to sleep, and their snoring keeps others awake.
David snores.
His 'friends' moved his bed out to the tractor carport.
Getting there.
14 aprile 1997, Australia ⋅ 22 °C
Over the next few weeks, the walls gradually grew.
We made the Benalla Ensign.
25 aprile 1997, Australia ⋅ 16 °C
It seemed that we had somehow got onto the local tourist map. People we didn't know would just turn up to have a look at what we were doing.
A reporter at the Benalla Ensign asked if he could run aLeggi altro
Roof on.
2 maggio 1997, Australia ⋅ 16 °C
29th April - 2nd May - the gutter and roof fixed.
Two sheets of iron were taken off to allow the chimney to exit the house. I was to replace them once the chimney was complete. The plumbers would thenLeggi altro
Chimney finished.
9 maggio 1997, Australia ⋅ 12 °C
The chimney is finished.
The back wall and the gables remain to be finished.
The stonework is finished.
25 maggio 1997, Australia ⋅ 12 °C
Not sure of the exact date ,but the stonies finished late May.
Now for the inside.
26 maggio 1997, Australia ⋅ 9 °C
The first thing to organise internally was the plastering. I had called three plasterers but when I said it was steel frame and ten foot ceilings, two weren't too interested. Graham 'Grubby' HollandLeggi altro
Jotul heater and Stanley stove.
28 maggio 1997, Australia ⋅ 16 °C
Stones were selected to make hearths for the stove and the heater.
Both had been held in place by standing them on bricks.
Starting with the stove, each one was held on a plank with a car jack at eachLeggi altro
Electrician and plumber back to fit out.
31 maggio 1997, Australia ⋅ 10 °C
Next on the list are the plumber and electrician to do their fit out.
After that it's painting.
Painting.
3 giugno 1997, Australia ⋅ 11 °C
Painting isn't my favourite job but it's a lot easier when drips and splatters don't matter that much.
A bit of plumbing.
10 luglio 1997, Australia ⋅ 7 °C
The bath and the handbasin in the loo were installed. Having the bath in place meant we had a shower.
A temporary kitchen sink and benches were used - melamine on trestles.
Skirting and architrave.
30 luglio 1997, Australia ⋅ 15 °C
Skirting was needed for each room.
Architrave was needed for:-
5 double doors (external)
1 single door (external)
17 windows
8 internal doors (2 sides)
1 linen press
All were pre-cut andLeggi altro

















































































