• One more dual lifting day at L7-CC!

    May 10, 2024, North Sea ⋅ ☁️ 18 °C

    On Thursday the 10th of May, two more modules from the L7-P & L7-Q platforms were taken away from the L7 Central Complex and safely brought back to transportation barges, moored at Den Helder.

    By lifting the remaining of the living quarter top modules, the first barge of the year 2024 had been completed and carefully towed to Vats, Norway for further recycling of the lifted modules!

    While involving both the Matador 3 and the Hebolift 10 for a sequenced operation, achieved within 12hrs, the transportation barges at Den Helder followed a similar sequence, with the first barge departure and following arrival to accommodate the freshly lifted L7-P module.

    Seven more offshore lifts to go for the 2024 year!