L7 Site Restitution

Following the progress of the L7 Site Restitution project Leggi altro
  • Inizio del viaggio
    9 ottobre 2022

    L7 EPRD Contract signature !

    11 ottobre 2022, Norvegia ⋅ ☁️ 9 °C

    On the 11th of October 2022, the TEPNL project team together with Aurélie Abiad, Managing Director of the affiliate, joined AF Offshore Decom at their Dismantling yard in Vats to officialize the EPRD contract!

    After a short 10 months of tendering, the full EPRD contract has been awarded to the Norwegian civil engineer and offshore decommissioning company: AF Offshore Decom.

    It comprises Topside and Jacket removal including Subsea assets such as pipelines and anode blocks. The aim remains simple: leave the L7 Site as free of any structures as when the affiliate received it more than 30 years ago.
    Leggi altro

  • EBS Mobilization Day!

    25 ottobre 2022, Inghilterra ⋅ ☁️ 14 °C

    As part of the full L7 Site Restitution project, a dedicated Environmental Baseline Study (EBS) will be carried out.

    The aim: assessing the current environmental status of the L7 field after more than 30 years of development and production!

    Gardline and their vessel, the Ocean Reliance have been selected to execute the offshore work, laboratory analyses and final reporting! The estimated offshore campaign length is around 28 days.
    Leggi altro

  • EBS Offshore operations at L7

    28 ottobre 2022, North Sea ⋅ 🌬 16 °C

    With more than 70 specific environmental stations to fully cover the L7 field, the EBS is focused on the platform's close surroundings, and up to 50 meters away, and also the OBM wells and infield locations.

    The main operations were:
    - Camera transects of the seabed to observe macrofauna/biodiversity
    - Seabed sampling by means of a Day Grab as depicted in the above picture
    - Seawater sampling at different depths by auto-triggering bottles
    - Collecting Plankton
    - eDNA sediment & water samples
    Leggi altro

  • Subsea operations mobilization date!

    11 febbraio 2023, Norvegia ⋅ 🌬 7 °C

    On the 11th of February, the 1st offshore removal campaign started after more than a year of tendering, engineering and preparation!

    Plan is to disconnect all the jackets of the L7 field from any pipeline, anti-scour frame and cables to allow complete structure removal in the future!

    For that purpose, the Olympic Delta from ReachSubsea has been selected, for a campaign lasting approximately 28 days!
    Leggi altro

  • Subsea works - First pipes for disposal!

    23 febbraio 2023, Olanda ⋅ ☁️ 8 °C

    On February 23, the first pipe sections removed from the L7-A and L7-N platforms have been offloaded at Den Helder!

    Although pre-measured onboard to verify the NORM free status of the pipes, a thorough lab analysis of the scratched samples will be performed to check for any HAZMAT presence before disposal.

    Next trip for the recovered pipes on the agenda: the dismantling yard for further processing and recycling!
    Leggi altro

  • 2nd Satellite, L7N in preparation!

    19 aprile 2023, North Sea ⋅ 🌬 9 °C

    After a successful preparation campaign at L7A, Hydra is now jacked-up at L7N for similar preparation works.
    On the agenda for a week: lifting points inspection, topside legs pinning, topside/jacket legs cutting, helideck opening for sling path clearance...!Leggi altro

  • Conductor removal scope at L7H

    24 aprile 2023, North Sea ⋅ 🌬 7 °C

    Currently jacked-up at L7H, the Hydra now faces an extended scope, now including the removal of the three (3) conductors.
    Cut during the P&A campaign at -6 meters below seabed, these conductors (weighing ~70mT each) are now ready to be picked-up, and lifted in sections on to the Hydra deck.
    This scope is in addition to the original topside preparation works required to allow for the L7H topside to be lifted later this year!
    Leggi altro

  • Preparation works at L7CC

    22 maggio 2023, North Sea ⋅ ⛅ 13 °C

    After more than 3 weeks warming-up with preparation works at the three satellites, now it's time to get started at the L7CC location!

    Considered as the most complicated and lengthy part of the L7 2023 preparation campaign, the central complex preparation comprises:
    - L7P with 7 modules splitting & lifting point reinstatements, including one milestone lift : the 90m high radio tower
    - L7PK topside and jacket preparation for lifting
    - L7Q topside preparation, including splices between modules (QE and QW).

    This first preparation campaign at L7CC is supposed to last for at least 1 month.
    Leggi altro

  • L7N Topside Lift

    21 agosto 2023, North Sea ⋅ ☀️ 18 °C

    Today, Matador 3 lifted the L7N topside and brought it back to Den Helder. It is the first heavy lift of the project after the removal campaign. Crew and vessel have been ready since the replacement of the Haringvlietbrug, but the summer has been exceptionally windy. Our patience has finally been rewarded and we are aiming for more later this week!Leggi altro

  • L7B&BB preparations

    31 ottobre 2023, North Sea ⋅ ☁️ 11 °C

    On the last day of October we completed a 3 week preparation campaign on L7B/BB.
    This iconic platform is our most challenging; home to a large seagull colony we had to wait for the breeding season to end. Moreover, a guiding system is being installed to replace the lower topside with a brand new module for CCS redevelopment .
    All in all, the platform is ready for the 2024 heavy lift campaign!
    Leggi altro

  • One more dual lifting day at L7-CC!

    10 maggio 2024, North Sea ⋅ ☁️ 18 °C

    On Thursday the 10th of May, two more modules from the L7-P & L7-Q platforms were taken away from the L7 Central Complex and safely brought back to transportation barges, moored at Den Helder.

    By lifting the remaining of the living quarter top modules, the first barge of the year 2024 had been completed and carefully towed to Vats, Norway for further recycling of the lifted modules!

    While involving both the Matador 3 and the Hebolift 10 for a sequenced operation, achieved within 12hrs, the transportation barges at Den Helder followed a similar sequence, with the first barge departure and following arrival to accommodate the freshly lifted L7-P module.

    Seven more offshore lifts to go for the 2024 year!
    Leggi altro

  • Lifting of P5,P6N,L7PK and L7C

    15 maggio 2024, North Sea ⋅ ☀️ 13 °C

    In the period 09-05 and 10-05 the "P5" module and the "Qwest" module were lifted by Hebolift 10 (P5) and Matador 3 (QW)
    Q west was the last lift on the second barge and the barge left shortly after installation and sea fastening.(picture in next footprint)
    At 18-05 the "P6North" module (facilitating former offices and Controlroom...) was removed from L7P .
    At 26-05 the L7PK top side was lifted by Hebolift 10 and at 18-06 the L7C top side was lifted from L7CC to complete the third barge.