L7B-BB Bridge removal
5 Aralık, North Sea ⋅ 🌬 9 °C
05-12 the bridge was removed successfully, next lift will be L7BB topside
Removal L7B -2 module
3 Aralık, North Sea ⋅ 🌬 10 °C
On 03 December the L7B-2 module was removed form the L7B platform , L7B-1 module with the celleardeck will stay in place , L7BB-B bridge , L7BB topside and the L7BB jkacket to be lifted.
UnfortunatelyOkumaya devam et
Removal L7B helideck and accommodation
29 Kasım, North Sea ⋅ 🌬 11 °C
Last night we successfully removed the L7B helideck and accommodation and placed it at the back of the DEME Innovation, next good weather window will be used to lift the process module /engine room ofOkumaya devam et
2025 L7CC-L7B-BB Removal campaign
26 Kasım, North Sea ⋅ ⛅ 8 °C
23-11-2025 the 2025 removal campaign has started in Middlesborough by mobilizing the DEME Innovation HLJUV (heavy lifting jack up vessel) for the removal of L7B3 & B2 module and L7BB topside and theOkumaya devam et
Toppling and demolition L7PK
25 Temmuz, Norveç ⋅ ☁️ 18 °C
The L7PK is toppled and the demolition has started , the final module of the project to be demolished in Vats .
The remaining parts of L7CC and L7B will be transported and demolished in theOkumaya devam et
Removal preparation with Skandi Inventor
19 Temmuz, North Sea ⋅ 🌬 19 °C
L7CC jacket removal preparations started with DSV Skandi Inventor, removal of the remaining's itself is planned for October 2025
Toppling and demolition of L7P1 module
2 Haziran, Norveç ⋅ ☁️ 10 °C
The L7P1 module has been toppled in week 22 and the demolition started straight after the toppling, after this module only the L7PK topside remaining to be Demolished in Vats Norway.
Toppling and demolition of L7Q1 Module
1 Mayıs, Norveç ⋅ ☁️ 14 °C
Medio April/May the L7Q1 module has been toppled fully upside down to make the demolition with the Big scissor more easy, unfortunately TEPNL has not been on site to make some pictures of theOkumaya devam et
Demolition L7C started
5 Mart, Norveç ⋅ 🌧 7 °C
05 March the L7C has been tipped over and the demolition started.
On the 8th of March the L7C has been toppled again on its side to improve and speed up the demolition , on 11-03 the complete topsideOkumaya devam et
P5 Module under demolition
8 Şubat, Norveç ⋅ ⛅ 0 °C
Today a start is made with de destruction of the P5 module, Destruction Machine Snohvit (snowy white) shows no mercy..
Demolition works Norway Q1 2024
6 Şubat, Norveç ⋅ ☀️ 5 °C
Some demolition progress over the last months: L7Q East and West , P6N with offices and Control room are completely demolished, P5 module with the turbine hall, L7C,L7PK , L7Q Cellar deck and the L7P1Okumaya devam et
Demolition activities L7Q and L7P
4 Aralık 2024, Norveç ⋅ ☁️ 1 °C
L7Q west module is fully demolished and L7Q east, P5 and P6 North (with control room) are prepared for full demolition.
Load in of the Barge 3
3 Aralık 2024, Norveç ⋅ ☁️ 2 °C
As from the 3rd of December the load in activities started of the Barge 3 carrying the Jackets of L7A/H/N on 04-12 the L7A jacket was set ashore, on 06-12 the barge was turned and the L7H jacket wasOkumaya devam et
Load-in Barge 4 & 5 October 2024
29 Ekim 2024, Norveç ⋅ ☁️ 7 °C
Barge 4 & barge 5 being unloaded in Vats for final demolition of the L7Q,L7P,L7PK and L7C modules
Barge 3 sailed to Norway October 2024
19 Ekim 2024, North Sea ⋅ 🌬 14 °C
17-10 the Barge 3 carrying the L7A/N/H jackets sailed safely to Vats Norway arriving 19-10 awaiting on unloading and final demolition
Removal Jackets L7A,L7H & L7N
10 Ekim 2024, North Sea ⋅ 🌬 12 °C
In September/October the jackets of the L7A, L7H and finally the L7N are removed and placed on the barge in Den Helder with the use of crane Barge "Rambiz" of company Scaldis.
The L7N jacket landedOkumaya devam et
Demolition activities L7CC & Satellites
5 Ağustos 2024, Norveç ⋅ ☁️ 18 °C
An overview of the several demolition works at the AF Decom environmental base in Vats Norway were in August/September 2024 the P3,P4 L7N and L7A are "recycled"
Lifting L7P P1 module
30 Temmuz 2024, North Sea ⋅ ⛅ 19 °C
In the period 30-31 July the L7P P1 module is lifted of.
Lifting L7Q-L7P bridge and L7Q1 module .
19 Temmuz 2024, North Sea ⋅ ⛅ 23 °C
In the period 19th till 22nd of July the bridge between L7Q-P and the L7Q 1 Module were lifted
Subsea cutting at L7CC and L7B
28 Haziran 2024, North Sea ⋅ 🌬 20 °C
As from end of June till 22nd of July the EDT Protea did subsea operations at L7CC and L7B platform
Load in second barge in Vats Norway
24 Mayıs 2024, Norveç ⋅ ⛅ 20 °C
In the period from 23-05 till 29-05 the second barge being unloaded at the demolition site of AFDecom in Vats Norway.
Lifting of P5,P6N,L7PK and L7C
15 Mayıs 2024, North Sea ⋅ ☀️ 13 °C
In the period 09-05 and 10-05 the "P5" module and the "Qwest" module were lifted by Hebolift 10 (P5) and Matador 3 (QW)
Q west was the last lift on the second barge and the barge left shortly afterOkumaya devam et
One more dual lifting day at L7-CC!
10 Mayıs 2024, North Sea ⋅ ☁️ 18 °C
On Thursday the 10th of May, two more modules from the L7-P & L7-Q platforms were taken away from the L7 Central Complex and safely brought back to transportation barges, moored at Den Helder.
ByOkumaya devam et
L7CC lifting has started
5 Mayıs 2024, North Sea ⋅ ☀️ 12 °C
An excellent start of the 2024 season with 3 removal lifts from the L7 central complex this week. On Monday the Hebo Lift 10 took the Q-west module and this morning the P3 module. Matador 3 came outOkumaya devam et
Load-in of L7-A,H&N topsides
11 Şubat 2024, Norveç ⋅ ☁️ 4 °C
Last week the topsides of L7-A, N & H were successfully loaded onto the AF environmental base in Vats. Stripped from hazardous materials while on the barge, they are now ready for further dismantlingOkumaya devam et